Natomas Levee Improvement Program

JANUARY 20, 2010 NLIP PROGRAM SCHEDULE
FEBRUARY 11, 2010 NLIP CONSTRUCTION PHASING MAPS:


Actual Work on NLIP is Executed in a Series of Contracts. To View the Aerial Extent (Footprint) of each Contract, CLICK on the word 'Footprint'

Award Date:
2010 - March
Sacramento River East Levee Phase 2B Reaches 5A-9B Improvement Project
Contract xxxx
Footprint
Award Date:
2009 Dec 10
Sacramento River East Levee Phase 2A Reaches 5A-9B Improvement Project
Contract  4047
Footprint
Award Date:
2009 Dec 10

SREL Phase 2B Reahes 5A-9B and Phase 3A Reaches 10-15 Tree Removal Project
Contract  4044
Footprint 
Award Date:
4043:
2009 Dec 10

4029:
2009 Mar 19
Phase 2 Woodland Mitigation and Enhancement Projects
Contract 
4043 & 4029
Footprint
  
Award Date:
2008 Dec

SREL Phase 2 Stucture Demolition and Tree Removal Project
Contract 4020
Footprint
  
     


IF YOU ARE A NATOMAS RESIDENT OR PROPERTY OWNER AND HAVE QUESTIONS ABOUT
THE PROJECT, PLEASE CONTACT BARB GUALCO OR JAY DAVIS
AT (916) 351-0600


2010
Feb 19

Final EIS - Phase 4a Landside Improvememts Project
2010
Feb. 18
Letter to Property Owners Adjacent to Levee Construction in
Reaches 1-9B
 Letter to Residents

2010
Jan. 21
Woodland Habitat Conservation and Mitigation Strategy
2010
Jan. 20
   Board of Senior Consultants
2010
Jan. 12
  U.S. Army Corps of Engineer's Levee Safety Program
2009
Nov. 1
8
  Phase 4b EIS/EIR Scoping Meeting
  Public Meeting Boards
2009
Nov. 5
  Notice of Preparation of an EIS/EIR on the Natomas Post-authorization   Change Report NLIP, Phase 4b Landside Improvements Project    
  PAC Report
2009
Nov. 3
Final EIR on the NLIP Phase 4a Landside Improvements Project
2009
Oct. 21
NLIP Safety Assurance Review Plan for Phases 3 & 4A
Safety Assurance Plan
2009
Sept. 29
U.S. Army Corps of Engineers Sacramento River Bank Protection Project at River Mile 73.5   Email to Garden Highway Residents
2009
Aug. 28
Draft EIS/EIR NLIP Phase 4a Landside Improvements Project

Apndx A - Part 1 Apndx A - Part 2 Appendix B Apndx C - Part 1 Apndx C - Part 2
Apndx C - Part 3 Apndx D - Part 1 Apndx D - Part 2 Apndx E - Part 1 Apndx E - Part 2
Appendix G
2009
Aug. 21
Final EIS on the NLIP Phase 3 Landside Improvements Project

Appendix
B-Part 1

Appendix
B-Part 3


2009
Aug. 20
SREL 2A Pre-Construction  Notice
2009
July 28
Levee Cutoff Wall 24/7 Construction for the Natomas Levee Improvement Program   Cutoff Wall Construction
2009
July 27
Natomas Levee Improvement Update   Report
2009
July 24
NLIP Contract 4032 Construction Update   Report
2009
July 10
Draft Relocation Plan for the Natomas Levee Improvement Program   DRAFT Relocation Plan
2009
July 9
Woodland Corridor and Perennial Grassland Design Consideration  Design Consideration
2009
July 8
Basis of Geometric Design for Relocated Irrigation and Drainage Canals Natomas Levee Improvement ProgramGeometric Design Report
2009
Summer
Army Corps of Engineers Construction in Natomas
Common Features Report
2009
May 15
Mitigation Monitoring and Reporting Program for the Natomas Levee Improvement Program Phase 3 Landside Improvement Project   MMRP
2009
May 11
2009
May 8
NLIP Phase II Safety Assurance Review Plan Approval
U.S. Army Corp of Engineers Memorandum
2009
May 6
NLIP Phase II Approval of LTMP and MMP
U.S. Fish and Wildlife Service Approval Letter
2009
May 1
Funding Agreement for State Cost Sharing with SAFCA on NLIP, $193 Million
Funding Agreement
2009
April 27

Natomas Levee Improvement Program Landside Improvements Project Phase 2 - Mitigation and Monitoring Plan & Programmatic Long-Term Management Plan

2009
April 13

Phase 4a Scoping Meeting

2009
April 7

Natomas Cross Canal Phase 2 and Sacramento River
East Levee Phase 1
Construction Update

2009
Mar. 27

Notice of Preparation, EIS/EIR on the NLIP, Phase 4A Landside
Improvements Project

Federal Register Posting

2009
Mar. 19

Woodland Relocation and Mitigation Update (with Photos)
Presentation

2009
Mar. 19

NLIP Program Update (for Full Report see Board Agenda Item 8)
2009
Mar. 16
NLIP Landside Improvements Project Draft Programmatic
Long-Term Management Plan
(
Currently being Reviewed by U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service and California Department of Fish and Game)
Draft LTMP
2009
Feb. 19
NLIP Proposition 1E Early Implementation Program
Area Plan Formulation Report

State Grant Application
2009
Feb. 19
2009
Feb. 13
2009
Feb. 4
Phase 2 Construction Notification
Phase 2 Construction Notification
2009
Jan. 29
California Department of Fish and Game 1602 Agreement :
1602 Agreement
2009
Jan. 21

Corps Record of Decision and Section 408 Approval NLIP Phase 2


2009
Jan. 16
2008
Dec. 28
Natomas Levee Improvement Program - Sacramento River East Levee Reaches 1 to 4A and Natomas Cross Canal Phase 2 Construction - Notice to Contractors
2008
Dec. 22
Natomas Levee Improvement Program - Natomas East Main Drainage Canal Update - Letter
2008
Nov. 18
2008
Nov. 14
Executive Director's NLIP Update - Report
2008
Nov. 14
2008
Oct. 22

NLIP Public Scoping Meeting Display Boards

Display Boards PDF

2008
Oct. 16
2008
Oct. 3
NLIP 2009 Pre-Construction Tree Removal Activity - Letter
2008
Oct. 3
RD1000 Board of Trustees Meeting - Agenda

2008
O
ct
. 2

Notice of Preparation of a Subsequent Environmental Impact Report - Natomas Levee Improvement Program Landside Improvements Project Phase 2 - NOP
2008
Sept. 30
RD1000 and SAFCA Proposed Joint Use Agreement -
Proposed Agreement
2008
Sept.12
Pritchard Lake Improvement Project - Hauling Activity Notice
2008 Aug. 21
2008
Aug. 21
2008
Aug. 21
NLIP Update - Staff Report
2008
Aug. 8

Phase 1B NLIP Construction Truck Routes Update - Letter

2008
July 29
Executive Director's NLIP Update - Report
2008
July 18
NLIP Phase 3 Project NOP - Notice of Preparation
2008
July 14
2008
July 11
NLIP Update
2008
July 3
NLIP Draft Environmental Impact Statement - Public Meeting Notice Public Notice
2008
June 27
Notification Letter Announcing 2008 NCC Construction - Letter
2008
June 19
SAFCA Board Action to Approve 2008 NCC Construction - Letter
2008
June 10
Environmental Impact Statement Notice of Availability - Notice of Availability
2008
June 4
Draft Environmental Impact Statement - 408 Permission and 404 Permit - Full Report

2008
May 15

2008
April 17
NLIP Update - Staff Report
2008
Mar. 20
NLIP Update - Staff Report
2008
Feb. 21
Evaluation of NLIP Levee Improvement Effects on Groundwater
2008
Feb. 21
NLIP Update - Staff Report
2008
Jan. 17
NLIP Update - Staff Report
2008
Jan. 9
NLIP Public Scoping Meeting - Public Scoping Meeting Flyer
2007
Dec. 17
Natomas Levee Improvement Program Update - Update Letter
2007
Nov. 29
2007
Nov. 29
Public Hearing Slideshow
Full Version
2007
Nov. 29
2007
Nov. 29
Public Hearing Transcript (Text)
Public Hearing Transcript - Final
2007
Sept.14
2007
Sept.
2006
July
Natomas Levee Evaluation Study - Final Report
NLES Study
2003
July


 