Contract 4106 - Sacramento River East Levee Phase 2C (Reach 9B) Levee Improvement Project, Sacramento County, CA

Bids Opened September 6,, 2011    Engineer's Estimate    $410,000. - $500,000.

Contract # Bid Order
COMPANY NAME
Bid Amt.
4106
1
NORDIC INDUSTRIES, INC
$ 385,250.00
4106
2
DESILVA GATES CONSTRUCTION, LP
$ 447,500.00
4106
3
ARIZA CONSTRUCTION, INC
$ 456,500.00
4106
4
FOUR M CONTRACTING, INC
$ 460,500.00
4106
5
ANDERSON DRAGLINE, INC
$ 483,350.00
4106
6
DIAMOND D GENERAL ENGINEERING, INC
$ 490,431.24
4106
7
TIECHERT CONSTRUCTION
$ 536,720.00
4106
8
RAMCON ENGINEERING, INC
$ 550,863.00
4106
9
GRANITE CONSTRUCTION COMPANY
$ 562,562.00
4106
10
LUND CONSTRUCTION CO.
$ 636,100.00

 

Contract 4105 - Sacramento River East Levee Phase 1E (Reach 2) Private Irrigation Facility Rehabilitation Project, Sacramento County, CA

Bids Opened September 6, 2011      Engineer's Estimate       $100,000 - $120,000.

Contract # Bid Order
COMPANY NAME
Bid Amt.
4105
1
AQUAMARINE CONTRACTORS, INC.
$293,360.00

 

Contract 4109 - Natomas Levee Improvement Program Phases 3 and 4A Woodland Mitigation and Ehancement Project

Bids Opened August 25, 2011              Engineer's Estimate       $1,500,000.

Contract # Bid Order
COMPANY NAME
Bid Amt.
4109
1
RIVER PARTNERS
$1,195,649.62
4109
2
RESTORATION RESOURCES
$1,199,860.00

 

Contract 4099 - Natomas Levee Improvement Program Borrow Site Leveling, Reclamation and Grassland Establishment Project

Bids Opened June 2, 2011              Engineer's Estimate       $!,200,000.

Contract # Bid Order
COMPANY NAME
Bid Amt.
4099
1
RESTORATION RESOURCES
$1,140,995.00
4099
2
RIVER PARTNERS
$1,281,774.28

 

Contract 4094 - Natomas Levee Improvement Program (NLIP) Phase 3 Native Grassland Establishment Project

Bids Opened April 28, 2011              Engineer's Estimate       $735,000.00

Contract # Bid Order
COMPANY NAME
Bid Amt.
4094
1
RIVER PARTNERS
$708,746.10
4094
2
SIERRA VIEW LANDSCAPE, INC.
$849,483.58
4094
3
SOIL TECH, INC.
$977,564.29

 

Contract 4069 - Sacramento River East levee Phase 3A Structure Demolition and Tree Removal Project, Sacramento County, CA

Bids Opened September 7, 2010             Engineer's Estimate      $565,000.00

Contract # Bid Order
COMPANY NAME
Bid Amt.
4069
1
ALL CLEAR INC.
$372,084.0O
4069
2
G W DEMOLITION, INC.
$479,477.00

 

Contract 4067 - Natomas Levee Improvement Program Phase 2 and Phase 3, Upper and Lower Giant Garter Snake/Drainage Canal Planting Project, Contract 4067

Bids Opened June 24, 2010             

Contract # Bid Order
COMPANY NAME
Bid Amt.
4067
1
RIVER PARTNERS
$336, 527.06
4067
2
RESTORATION RESOURCES
$518,319.00

 

Contract 4066 - California Native Grassland Establishment Project for the Natomas Cross Canal (NCC) and Sacramento River East Levee (SREL) Reaches 1 to 4, including Levee Slopes, Seepage Berms and O&M and Utility Corridors

Bids Opened May 27, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4066
1
RESTORATION RESOURCES
$739,901.29
4066
2
RIVER PARTNERS
$790,365.69

 

Contract 4046 - Natomas Levee Improvement Program - Sacramento River East Levee Phase 2b (Reaches 5A through 9B) Improvements, Elkhorn Irrigation Canal Phase 2b Relocation, Giant Garter Snake/Drainage Canal Phase 2A Construction, Elkhorn Pumping Plant Modification, Natomas Cross Canal South Levee Phase 2b Improvement Project, Sacramento and Sutter Counties, California

Bids Opened April 13, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4046
1
$34,400,336.40.
4046
2
$37,732,673.00
4046
3
$38,847,979.80
4046
4
$38,872,789.12
4046
5
$38,891,259.50  
4046
6
$39,973,212.00  
4046
7
$41,284,911.00  
4046
8
$41,436,221.00  
4046
9
$42,139,248.00  
4046
10
$43,083,701.00  

 

Proposal Results - Natomas Levee Improvement Program Local Nurseries Plant Propagation and Procurement.

Bids Opened March 8, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
3/8/2010
1
HARTLAND NURSERY
$58,619.50
3/8/2010
2
HIGH RANCH NURSERY, INC
$79,090.00
3/8/2010
3
CORNFLOWER FARMS
$93,637.75



Contract 4055 -
Natomas Levee
Improvement Program Phase 2 Woodland Corridor Mitigation and Enhancement Project

Bids Opened March 4, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4055
1
AD LAND VENTURE
$497,499.14
4055
2
RIVER PARTNERS
$506,132.13
4055
3
RESTORATION RESOURCES
$523,497.90
4055
4
SMP SERVICES INC.
$836,486.39

 

Contract 4053 - Sacramento River East Levee Phase 1C (Reaches 1-2) Improvement Project Private River Diversion Pump Replacement, Sutter County, CA

Bids Opened January 21, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4053
1
ARIZA CONSTRUCTION, INC
$493,750.00
4053
2
HOWK SYSTEMS
$506,440.00
4053
3
McGUIRE AND HESTER
$541,740.00
4053
4
MARTECH
$598,753.00


Contract 4047 -
Sacramento River East Levee Phase 2A (Reaches 5A-9B) Improvement Project Structure Demolition and Tree Removal, Elkhorn Irrigation Canal Phase 2A Relocation, and Private Irrigation Facility Relocation, Sacramento County and Sutter County, CA

Bids Opened December 1, 2009

Contract # Bid Order
COMPANY NAME
Bid Amt.
4047
1
TEICHERT CONSTRUCTION
$2, 863,117.70
4047
2
MCGUIRE AND HESTER
$3, 084,657.10
4047
3
DESILVA GATES CONSTRUCTION L.P.
$3,086,095.00
4047
4
NORDIC INDUSTRIES INC.
$3,265,958.00
4047
5
INDEPENDENT CONSTRUCTION CO.
$3,622,227.00
4047
6
LISTER CONSTRUCTION
$3,335,145.00
4047
7
WOOD BROS. INC
$3,725,797.25
4047
8
ALLEN ENGINEERING CONTRACTOR INC
$3,877,398.00
4047
9
FORD CONSTRUCTION CO, INC.
$4,794,396.00

 

Contract 4044 - Natomas Levee Improvement Program - Sacramento River East Levee Phase 2B (Reaches 5A-9B) and Phase 3 (Reaches 10-15) Tree Removal Project, Sacramento County, California.

Bids Opened December 1, 2009

Contract # Bid Order
COMPANY NAME
Bid Amt.
4044
1
SOIL ENTERPRISES INC.
$140,190.00
4044
2
KK ENTERPRISE
$226,000.00
4044
3
W.C. MALONEY INC.
$293,357.50
4044
4
ALLCLEAR INC.
$349,993.00
4044
5
CLEARY BROS. LANDSCAPE
$562,190.00
4044
6
THE PROFESSIONAL TREE CARE CO.
$1,194,460.00



Contract 4043-
Natomas Levee Improvement Program Phase 2 Woodland Corridor Mitigation and Enhancement Project

Bids Opened November 24, 2009

Contract # BBid Orderr
Company Name
Bid Amt.
4043
1
AD LAND VENTURE
$452,570.61
4043
2
RESTORATION RESOURCES
$587,272.10
4043
3
SMP SERVICES, INC.
$766,881.53
4043
4
RIVER PARTNERS
$779,618.95



Contract 4037 -
Sacramento River East Levee Phase 2A (Reach 5A through 9B) Structure Demolition and Tree Removal, Elkhorn Irrigation Canal Phase 2A Relocation and Giant Garter Snake/Drainage Canal Phase 2A Construction Project

Bids Opened October 8, 2009

Contract # BBid Orderr
COMPANY NAME
Bid Amt.
4037
1
DESILVA GATES CONSTRUCTION
$3,156,651.00
4037
2
INDEPENDENT CONSTRUCTION
$3,548,108.00
4037
3
WOOD BROS. INC.
$3,588,828.00
4037
4
NORDIC INDUSTRIES, INC.
$3,666,666.00
4037
5
MCGUIRE AND HESTER
$3,671,489.00
4037
6
TEICHERT CONSTRUCTION
$3,749,736.50
4037
7
LISTER CONSTRUCTION
$4,145,578.00

 

Contract 4032 - Sacramento River East Levee Phase 1B (Reaches 2 through 4b), Elkhorn Irrigation Canal Phase 1 Relocation and Giant Garter Snake/Drainage Canal Phase 1 Construction Project, Sacramento County and Sutter County, CA

Bids Opened July 2, 2009

Contract # BBid Orderr
Company Name
Bid Amt.
4032
1
INDEPENDENT CONSTRUCTION CO. $21,495,971.00
4032
2
DESILVA GATES CONSTRUCTION L.P. $22,982,964.00
4032
3
NORDIC INDUSTRIES $25,550, 304.00
4032
4
TEICHERT CONSTRUCTION $25,797,861.50
4032
5
WOOD BROS. $29,911,592.50
4032
6
FLATIRON WEST, INC. $31,730,969.00
4032
7
FORD CONSTRUCTION
$

 

Contract 3980 - Natomas Cross Canal Phase 2 and Sacramento River East Levee Phase (Reach1) Improvement Project

Bids Opened April 2, 2009

Contract 4066 - Natomas Levee Improvement Program - Sacramento River East Levee Phase 2b (Reaches 5A through 9B) Improvements, Elkhorn Irrigation Canal Phase 2b Relocation, Giant Garter Snake/Drainage Canal Phase 2A Construction, Elkhorn Pumping Plant Modification, Natomas Cross Canal South Levee Phase 2b Improvement Project, Sacramento and Sutter Counties, California

Bids Opened April 13, 2010

 

 

Contract 4046 - Natomas Levee Improvement Program - Sacramento River East Levee Phase 2b (Reaches 5A through 9B) Improvements, Elkhorn Irrigation Canal Phase 2b Relocation, Giant Garter Snake/Drainage Canal Phase 2A Construction, Elkhorn Pumping Plant Modification, Natomas Cross Canal South Levee Phase 2b Improvement Project, Sacramento and Sutter Counties, California

Bids Opened April 13, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4046
1
$34,400,336.40.
4046
2
$37,732,673.00
4046
3
$38,847,979.80
4046
4
$38,872,789.12
4046
5
$38,891,259.50  
4046
6
$39,973,212.00  
4046
7
$41,284,911.00  
4046
8
$41,436,221.00  
4046
9
$42,139,248.00  
4046
10
$43,083,701.00  

 

 

Proposal Results - Natomas Levee Improvement Program Local Nurseries Plant Propagation and Procurement.

Bids Opened March 8, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
3/8/2010
1
HARTLAND NURSERY
$58,619.50
3/8/2010
2
HIGH RANCH NURSERY, INC
$79,090.00
3/8/2010
3
CORNFLOWER FARMS
$93,637.75



Contract 4055 -
Natomas Levee
Improvement Program Phase 2 Woodland Corridor Mitigation and Enhancement Project

Bids Opened March 4, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4055
1
AD LAND VENTURE
$497,499.14
4055
2
RIVER PARTNERS
$506,132.13
4055
3
RESTORATION RESOURCES
$523,497.90
4055
4
SMP SERVICES INC.
$836,486.39

 

Contract 4053 - Sacramento River East Levee Phase 1C (Reaches 1-2) Improvement Project Private River Diversion Pump Replacement, Sutter County, CA

Bids Opened January 21, 2010

Contract # Bid Order
COMPANY NAME
Bid Amt.
4053
1
ARIZA CONSTRUCTION, INC
$493,750.00
4053
2
HOWK SYSTEMS
$506,440.00
4053
3
McGUIRE AND HESTER
$541,740.00
4053
4
MARTECH
$598,753.00


Contract 4047 -
Sacramento River East Levee Phase 2A (Reaches 5A-9B) Improvement Project Structure Demolition and Tree Removal, Elkhorn Irrigation Canal Phase 2A Relocation, and Private Irrigation Facility Relocation, Sacramento County and Sutter County, CA

Bids Opened December 1, 2009

Contract # Bid Order
COMPANY NAME
Bid Amt.
4047
1
TEICHERT CONSTRUCTION
$2, 863,117.70
4047
2
MCGUIRE AND HESTER
$3, 084,657.10
4047
3
DESILVA GATES CONSTRUCTION L.P.
$3,086,095.00
4047
4
NORDIC INDUSTRIES INC.
$3,265,958.00
4047
5
INDEPENDENT CONSTRUCTION CO.
$3,622,227.00
4047
6
LISTER CONSTRUCTION
$3,335,145.00
4047
7
WOOD BROS. INC
$3,725,797.25
4047
8
ALLEN ENGINEERING CONTRACTOR INC
$3,877,398.00
4047
9
FORD CONSTRUCTION CO, INC.
$4,794,396.00

 

Contract 4044 - Natomas Levee Improvement Program - Sacramento River East Levee Phase 2B (Reaches 5A-9B) and Phase 3 (Reaches 10-15) Tree Removal Project, Sacramento County, California.

Bids Opened December 1, 2009

Contract # Bid Order
COMPANY NAME
Bid Amt.
4044
1
SOIL ENTERPRISES INC.
$140,190.00
4044
2
KK ENTERPRISE
$226,000.00
4044
3
W.C. MALONEY INC.
$293,357.50
4044
4
ALLCLEAR INC.
$349,993.00
4044
5
CLEARY BROS. LANDSCAPE
$562,190.00
4044
6
THE PROFESSIONAL TREE CARE CO.
$1,194,460.00



Contract 4043-
Natomas Levee Improvement Program Phase 2 Woodland Corridor Mitigation and Enhancement Project

Bids Opened November 24, 2009

Contract # BBid Orderr
Company Name
Bid Amt.
4043
1
AD LAND VENTURE
$452,570.61
4043
2
RESTORATION RESOURCES
$587,272.10
4043
3
SMP SERVICES, INC.
$766,881.53
4043
4
RIVER PARTNERS
$779,618.95



Contract 4037 -
Sacramento River East Levee Phase 2A (Reach 5A through 9B) Structure Demolition and Tree Removal, Elkhorn Irrigation Canal Phase 2A Relocation and Giant Garter Snake/Drainage Canal Phase 2A Construction Project

Bids Opened October 8, 2009

Contract # BBid Orderr
COMPANY NAME
Bid Amt.
4037
1
DESILVA GATES CONSTRUCTION
$3,156,651.00
4037
2
INDEPENDENT CONSTRUCTION
$3,548,108.00
4037
3
WOOD BROS. INC.
$3,588,828.00
4037
4
NORDIC INDUSTRIES, INC.
$3,666,666.00
4037
5
MCGUIRE AND HESTER
$3,671,489.00
4037
6
TEICHERT CONSTRUCTION
$3,749,736.50
4037
7
LISTER CONSTRUCTION
$4,145,578.00

 

Contract 4032 - Sacramento River East Levee Phase 1B (Reaches 2 through 4b), Elkhorn Irrigation Canal Phase 1 Relocation and Giant Garter Snake/Drainage Canal Phase 1 Construction Project, Sacramento County and Sutter County, CA

Bids Opened July 2, 2009                                     

Contract # BBid Orderr
Company Name
Bid Amt.
4032
1
INDEPENDENT CONSTRUCTION CO. $21,495,971.00
4032
2
DESILVA GATES CONSTRUCTION L.P. $22,982,964.00
4032
3
NORDIC INDUSTRIES $25,550, 304.00
4032
4
TEICHERT CONSTRUCTION $25,797,861.50
4032
5
WOOD BROS. $29,911,592.50
4032
6
FLATIRON WEST, INC. $31,730,969.00
4032
7
FORD CONSTRUCTION
$

 

Contract 3980 - Natomas Cross Canal Phase 2 and Sacramento River East Levee Phase (Reach1) Improvement Project

Bids Opened April 2, 2009

 
Contract #
Bid Orderr
Company Name
Bid Amt.
3980
1
TEICHERT CONSTRUCTION $21,495,971.00
3980
2
NORDIC INDUSTRIES, INC. $22,222,221.00
3980
3
DESILVA GATES CONSTRUCTION L.P.. $22,982,964.00
3980
4
INDEPENDENT CONSTRUCTION $23,281,916.75
3980
5
FLATIRON WEST, INC. $24,149,770.80
3980
6
SEMA CONSTRUCTION, INC. $24,834,725.50
3980
7
TOP GRADE CONSTRUCTION, INC. $24,965,650.00
3980
8
FORD CONSTRUCTION COMPANY, INC. $25,316,064.00
3980
9
KIEWIT PACIFIC $27,761,000.00
3980
10
SUKUT CONSTRUCTION, INC. $28,384,566.50
3980
11
RGW CONSTRUCTION, INC. $28,623,512.50
3980
12
GRANITE CONSTRUCTION CO. $31,569,786.15

 

 